Preventive Maintenance Programs for Water & Sewer Utilities (CMOM/SSMP‑Aligned)
Introduction
Hinterland Group designs and executes preventive maintenance programs for water, wastewater, and stormwater utilities across the Southeast—built around asset condition data, risk-based prioritization, and seamless handoffs to your CMMS/GIS. Our PRIME service model—Pipeline Rehabilitation, Repair & Replacement, Inspection, Maintenance, and Evaluation & Assessment—underpins CMOM/SSMP-aligned plans that minimize SSOs, extend asset life, and control lifecycle cost.
Program objectives and scope
-
Establish continuous condition assessment for gravity mains, force mains, laterals, manholes, lift stations, and critical stormwater structures.
-
Standardize data collection to support CMOM/SSMP documentation and audits.
-
Prioritize renewal using a transparent risk matrix (likelihood of failure × consequence of failure).
-
Convert field findings into actionable work orders and budget scenarios.
-
Provide minimally disruptive rehabilitation options (CIPP, geopolymer spincast, sliplining, pipe bursting) performed in-house for best‑value delivery. See Services.
Standards alignment: CMOM/SSMP and inspection taxonomies
Our preventive programs are structured to support utility CMOM/SSMP practices and produce inspection deliverables that map to common industry taxonomies used for pipelines and manholes (e.g., PACP/MACP-style defect catalogs, grading, and asset attributes). Where a utility already uses a standard schema, we align our data dictionary, codes, and media packaging to your requirements.
Field methods and QA controls
-
Cleaning and CCTV: Vactor-based cleaning followed by robotic CCTV at calibrated footage; pre/post-cleaning verification. See Inspection.
-
Manhole assessments: Visual/measure-up, infiltration/defect logging, frame adjustment and coating recommendations; compatible with coating systems referenced in Repair & Replacement.
-
Lift station checks: Mechanical/electrical observations, bypass planning, panel condition, alarms, and resiliency options; supported by in‑house electrical crews and bypass design per Repair & Replacement.
-
Safety: Daily tailboards, confined space protocols, and OSHA‑certified supervision; see About.
Data products and deliverables
Below is a representative set of outputs produced on PM rounds and targeted assessment projects.
| Deliverable | What it contains | Primary use | Notes |
|---|---|---|---|
| Condition reports | Summaries by basin/beat with defect counts, risk ranks, renewal recommendations | CMOM/SSMP documentation, budgeting | PDF and data files packaged with media references |
| CCTV media set | MP4 video, still frames, continuous footage index | Engineering review, rehab scoping | Linked to asset IDs and chainage |
| Defect catalog | Observations with standardized codes, severity, joint/segment locations | Prioritization, rehab design | Compatible with common pipeline/manhole schemas |
| Manhole inventory | Rim/invert, depth, material, defects, infiltration, rehabilitation needs | Coating programs, I/I reduction | Supports coating submittals and QA |
| Work-order pack | Ready-to-load tasks with activity type, location, estimated hours and traffic needs | CMMS ingestion | Aligned to your activity and asset codes |
| Executive dashboard | KPIs, heatmaps, progress vs. plan, cost curves | Stakeholder updates | Issued on the Reporting Cadence below |
CMMS/GIS handoff and exports
-
We deliver structured exports that align to your CMMS/GIS data model (asset keys, activity codes, status values). Where helpful, we provide field mapping to your schemas and include location metadata suitable for GIS.
-
Media packaging includes deterministic file names and index files linking observations to timecodes and footage chainage.
-
For utilities without a current system, we provide simple tabular exports that can be ingested later without rework.
Reporting cadence
-
Weekly: Field progress log (segments inspected, cleaned, exceptions), emerging risks, traffic/bypass look‑ahead.
-
Monthly: Program dashboard with defect distributions, risk heatmaps, recommended work orders, change log.
-
Quarterly/Phase-end: CMOM/SSMP packet—methods, QA/QC, summary of findings, risk-ranked renewal plan, budget and schedule scenarios, lessons learned.
Risk‑based priority matrix
We standardize prioritization with a transparent scoring model so stakeholders understand “why now.”
-
Likelihood of Failure (LoF): structural defects, infiltration, material/age, surcharge history, hydrogen sulfide exposure, soil/groundwater, root intrusion, CCTV confidence.
-
Consequence of Failure (CoF): proximity to customers/critical facilities, overflow sensitivity, traffic impacts, environmental receptors, replacement complexity and cost.
-
Scoring: LoF 1–5 × CoF 1–5 → risk 1–25 with color bands (low/medium/high/critical). Ties are broken by service criticality and cost‑per‑risk‑point of candidate fixes.
Rehabilitation pathways (performed in‑house)
-
Cured‑in‑Place Pipe (CIPP) for diameters from service laterals to large mains; see Pipe Rehabilitation and regional CIPP pages for capabilities (Florida, Georgia, North Carolina, South Carolina).
-
Geopolymer spincast and manhole coatings for structural restoration and I/I reduction; see Repair & Replacement.
-
Pipe bursting and sliplining to upsize or replace when lining is not optimal; see Services.
Florida municipal examples
-
City of West Palm Beach: multi‑street water/sewer/drainage improvements with sanitary CIPP lining; see Nottingham Water Main & Drainage Project.
-
Fort Pierce Utilities Authority: on‑call water/wastewater underground utility installation and repairs; see FPUA Force Main Work.
-
Charlotte County: stormwater collection system rehabilitation; see Charlotte County Project.
-
Indian River County: water main and force main work; see Indian River Project.
-
Martin County: emergency flooding services and stormwater rehabilitation; see Martin County.
-
Hallandale Beach: raw water pipeline installation and gravity sewer replacement; see Hallandale Project.
Emergency readiness and resiliency
Our PM programs are backed by 24/7 response and large‑event surge capacity for storms and flooding, including bypass pumping, point repairs, emergency coatings, and debris removal. See Emergency Storm & Flood Response and regional disaster recovery support for recent events (Hurricane Helene).
Why Hinterland Group
-
End‑to‑end delivery: inspection, data, risk, design‑build rehabilitation, electrical, and bypass—all in‑house. See Services.
-
Minimal disruption: trenchless methods that preserve streetscapes and operations; see Pipe Rehabilitation.
-
Safety culture: OSHA‑certified leadership and proven protocols; see About.
-
Southeastern coverage with rapid mobilization; see Markets We Serve.
-
Structured plans: annual Maintenance Plans that convert findings into executable work.
Getting started: intake form (copy/paste into your email)
Provide the following and our team will return a draft CMOM/SSMP‑aligned PM plan with scope, schedule, and budget options.
-
Utility name, point of contact, phone/email
-
Service area (city/county, basins/pressure zones), traffic constraints, access notes
-
Asset inventory: miles by pipe material/diameter/era; number of manholes; lift stations (count, duty/standby, telemetry); critical stormwater structures
-
Known pain points: SSO history, I/I hotspots, corrosion, surcharge, low pressure, flooding
-
Current systems: CMMS and GIS platforms; asset ID conventions; activity codes; desired import format
-
Inspection standards in use (if any) and preferred defect taxonomy
-
Media deliverables: video/still preferences, file naming, retention policy
-
Reporting preferences and cadence; stakeholder audiences
-
Contract model and timeline
Email the completed intake to the contacts at Contact Us.